Analisa Cost Overruns pada Beberapa Proyek Konstruksi di Kota Ambon
DOI:
https://doi.org/10.51135/manumatav3i1p26-33Keywords:
Project, Construction, Cost, OverrunsAbstract
Construction project is a process where plans and specifications of the planner converted into the physical structure, the greater a project means the more complex mechanism which means the more problems faced, because if not properly handled it will result in the impact of one of the cost overruns.
This study aims to know the factors cause of the cost overruns and to minimize the factors cause of the cost overruns on construction projects in the city Ambon. research conducted through the spread of questionnaires, with the goal of respondents is director, manejer project, site engineer, supervisory field with sub field work of the building, before the questionnaire was used to measure the variable the first tested the validity and reliability of using SPSS.
The results showed, factors cause of the cost overruns construction projects in accordance with the rating that is, the delay schedule for the influence of the weather (8,94%), data and information project incomplete (8,82%), the price increases material (8,68%), the high wage labor (8,68%). to minimize the factors cause of the cost overruns above then it must be completed prior to the main structure and the roof so that the work in the building can be done although weather conditions rain, surveying the early before the signature of the contract to the data and information project can know more clearly, making stock meterial and mengorder stuff before going price increases material, emphasizing wage labor but not reduce the quality of any workers.References
Asiyanto, (2005), Construction Project Cost Management, Jakarta:Pradnya Paramita
Barie, D.S. Paulson, Jr. B.C. dan Sudinarto. 1995. Manajemen Konstruksi Profesional. Penerbit Erlangga. Jakarta.
Dipohusodo, Istimawan, 1996, Manajemen Proyek dan Konstruksi Jilid 2, Kanisius, Yogyakarta.
Ervianto, W.I., 2002, Manajemen Proyek Konstruksi, Penerbit PT Andi, Jakart
Fahira, 2005 Faktor faktor penyebab terjadinya pembengkakan biaya pada proyek konstruksi gedung di Makasar. ITS Surabaya.
Indriani, Santoso. 1999. “Analisa Overruns Biaya pada Beberapa Tipe Proyek Konstruksiâ€. Dimensi Teknik Sipil. Volume 1.
Rizal, 1996. Pengendalian Proyek Dengan Mengintegrasi Penyimpangan Biaya ITB Bandung
Soeharto, Iman.1995, Manajemen Proyek: Dari Konseptual sampai Operasional. Penerbit Erlangga. Jakarta.
Santoso, 2002, Analisis Faktor-Faktor Penyebab Cost Overrun, Laporan penelitian Universitas Kristen Petra Surabaya
Sarwono, Jonathan. 2006, Metode Penelitian Kuantitatif dan Kualitatif, Yogyakarta : Graha Ilmu
Wikipedia, Februari 2017. “Konstrusiâ€, [Online] Diunduh melalui: https://id.wikipedia.org/wiki/Konstruksi
Downloads
Published
Issue
Section
License
Authors who publish with this journal agree to the following terms:- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).