Analisa Keterlambatan Waktu Pelaksanaan Proyek Konstruksi Di Kota Ambon : Klasifikasi Dan Peringkat Dari Penyebab-Penyebabnya
DOI:
https://doi.org/10.51135/manumatav6i1p19-23Keywords:
Cause, Delay, ContractorAbstract
Successful completion of a timely construction project is one of the most important goals for both owners and contractors. A project is likely to experience delays if planning, provision and implementation are not appropriate. This research aims to determine the factors that cause the delay of project implementation time in the construction project of qualification building M1 and M2. The research was carried out through the distribution of questionnaires, with the target respondents being directors, site managers, and foremen with sub-sector building work. Before the questionnaire was used to measure the variables then first tested the validity and reliability by using the software program IBM SPSS 22.0. The results of the research indicate that the factors that cause the delay in the implementation of the project are crucial is, Funding of unplanned project activity (funding difficulties in contractor), the classification of the cause is the Resource Readiness / Preparation Aspect, with the approval level for the respondent of the Director is 88.192% , for Site Manager respondents is 87.273%, for the respondent the Mandor is 84.545%.
References
Messah, Y. 2008. Kajian Keserasian Undang-Undang Jasa Konstruksi No. 18 tahun 1999 dengan kepres No. 80 tahun 2003 dalam Pengadaan Jasa Pemborong Konstruksi oleh Pemerintah.Fakultas Teknik Sipil dan Lingkungan ITB.
Messah,Y.A.,et.al,“Kajian Penyebab Keterlambatan Pelaksanaan Proyek Konstruksi Gedung di Kota Kupang.Jurnal Teknik Sipil Volume 2 Universitas Nusa Cendana.
Proboyo, Budiman,“Keterlambatan Waktu Pelaksanaan Proyek : Klasifikasi dan Peringkat Penyebab-Penyebabnya.Dimensi Teknik Sipil Volume 1 Universitas Kristen Petra.
Kusjadmikahadi, R.Amperawan,1999.“Studi Keterlambatan Kontraktor dalam melaksanakan Proyek Konstruksi di Daerah Istimewa Yogyakarta.Yogyakarta
Sarwono, Jonathan.2006.Metode Penelitian Kuantitatif dan Kualitatif.Graha Ilmu, Yogyakarta.
Soeharto, Iman.1995. Manajemen Proyek : Dari Konseptual sampai Operasional. Penerbit Erlangga.Jakarta.
Umar, Husein.2005,Metode Penelitian untuk Skripsi dan Tesis Bisnis.Penerbit Rajawali Pers.Jakarta.
Downloads
Published
Issue
Section
License
Authors who publish with this journal agree to the following terms:- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).