Kajian Potensi Mikrohidro Di Sungai Wai Tona Negeri Nuniali, Kecamatan Taniwel, Kabupaten Seram Bagian Barat
DOI:
https://doi.org/10.51135/manumatav6i2p38-45Keywords:
Micro-hydro, river discharge, Head, PowerAbstract
Micro hydro power plant (MHP) is a technology by utilizing the flow of the river to generate electricity. The aim of this study is to analyze the flow and height of the falling water (head), determine the type of turbine and analyze capacity obtained when applied to the concept of micro-hydro on the river Wai State Tona Nuniali Taniwel District of West Seram regency. The flow rate and high water fall (head) at Wai Tona river is one of the determining factors to determine the amount of power capacity will be obtained. Data-data used in the analysis is the primary data (flow rate) obtained from the calculation of the flow velocity and the cross-sectional area of the river Wai Tona using a measuring instrument types C31 current meter. Based on the results of the data analysis, the obtained flow rates at the cross-section diameter of 0.95159 m3 / s at an elevation of 72 meters above sea level. It also obtained high value falling water (head) of 50 m will be able to determine the type of turbine. The turbine is determined kind is francis turbine. The results of the data analysis will then be obtained large electric power of 356.703 kW or 0.356 MW.
References
Aprianto. 2014. Analisa Potensi Air Terjun untuk Pembangkit Listrik Mikrohidro di Kawasan Wisata Girmanik (Jurnal)
Asrori, Eko Yudiyanto. 2015. Perencanaan Turbin Air Pembangkir Listrik Tenaga Mini Hidro (Studi Kasus Proyek PLTM Buleleng 2 x 600 kW).
(Jurnal Internet) diakses pada tanggal 04 Oktober 2019
Direktorat Jenderal Sumber Daya Air. 2009. Prosedur dan Instruksi Kerja Pengukuran Debit Sungai dan Saluran Terbuka. Jakarta
D P D Suparyawan*, I N S Kumara, W G Ariastina. 2017. Studi Perencanaan Pembangkit Listrik Mikrohidro di desa Sambangan Kabupaten Buleleng Bali (Jurnal Internet) di akses pada tanggal 18 Maret 2019
ngkos K, Dony S, Asep R, Ii Supiandi. 2017. Kaji Analitik Potensi Daya Listrik PLTMH di Air Terjun Muara Jaya Desa Argamukti Kabupaten Majalengka Provinsi Jawa Barat. (Jurnal Internet). Di akses pada 23 Maret 2019
Modul Manual Pembangunan PLTMH, Institut Bisnis dan Ekonomi Kerakyatan.
SNI 3408-2015, Tata cara pengukuran kecepatan aliran pada uji model hidraulik fisik (UMH-Fisik) dengan alat ukur arus tipe baling – baling.
Sri Sukamta, Adhi Kusmantoro. 2013. Perencanaan Pembangkit Listrik Tenaga Mikrohidro (PLTMH) Jantur Tabalas Kalimantan Timur. (Jurnal Internet) di akses pada 03 Agustus 2019
Willy C Rompies, Lingkan K, Fuad H, J D Mamoto. 2013. Analisis Potensi Sumber Daya Air Sungai Kayuwatu Wangko untuk Perencanaan Pembangkit Listrik di Desa Karor Kec. Lembean Timur Kabupaten Minahasa. (Jurnal Internet) di akses pada 23 Maret 2019
Downloads
Published
Issue
Section
License
Authors who publish with this journal agree to the following terms:- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).