Analisis Kinerja Waktu Pada Pelaksanaan Pembangunan Gedung Kantor Bahasa Provinsi Maluku Menggunakan Metode Earned Value

Penulis

  • Suryanto intan UNIVERSITAS KRISTEN INDONESIA MALUKU
  • Thobyhend J M Sahureka UNIVERSITAS KRISTEN INDONESIA MALUKU
  • Yeremia Sahuleka UNIVERSITAS KRISTEN INDONESIA MALUKU

DOI:

https://doi.org/10.51135/manumatav10i2p153-161

Kata Kunci:

Waves, Beach, Erosion, Sedimentation, Influence

Abstrak

Infrastructure development is one of the main indicators of a region's economic growth. One of the important infrastructures is the government office, which is the center of administration and community services. the construction of the Maluku Province Language Office Building with the Implementing Contractor PT. PRIMA KONSTRUKSI. which was agreed with a budget of Rp. 28,194,890,000.00 with the duration of project implementation from March 15, 2023 to December 31, 2023 or approximately for 10 months to build the Maluku Province Language Office Building. The purpose of this is to analyze the performance of the time and schedule of the (Lukas Mose et al., 2022)implementation of the Maluku Province Language Office Building Construction using the Earned Value Method. The method used in this study is the Earned Value Method of control used to control the time, schedule and performance of the project. by calculating indicators from the BCWP and BCWS values to obtain the Schedule variance value or (SV), Schedule performance index or (SPI) and Time Estimated or (TE) and calculating indicators from the BCWP and BCWS values to obtain the Schedule performance index value or (SPI) and Time Estimated or (TE).The results obtained at the project completion time based on Time Estimated (TE) are 44 weeks, so the project is 2 weeks late from the total planned project completion time of 42 weeks. And the Schedule Performance Index (SPI) value of 0.958 indicates that the project is experiencing a delay of 2 weeks from the total planned time of project completion of 42 weeks. And the Schedule Performance Index (SPI) value of 0.958 indicates that the project is 4.19% late from the original plan of 100.00% with a work realization of 95.81%.

Referensi

(CERC), C. E. (1984). Shore Protection Manual .

Washington D.C.: US Army Corps of

Engineers.

(1997). Dalam I. Soeharto, Menajemen Proyek (hal.

.

Adinata, S., & Alfa, A. (2020). PENERAPAN METODE

KONSEP NILAI HASIL (EARNED VALUE

CONCEPT) PADA PROYEK

PENINGKATAN JALAN ASPAL DI

LOKASI F4 (SUNGAI SIRIH). Seloda

Mayang, 109-117.

Dipohusodo, I. (1996). Manajemen Proyek &

Konstruksi.Kanisius. Jogjakarta.

Garditjo, E. (2017). Pengendalian Jadwal dan Anggaran

Terpadu dengan Metode Earned Value Analisis

Pada PEkerjaan Konstruksi. UkaRsT, 19-26.

Hardiyatmo, H. C. (2007). Pemeliharaan Jalan Raya.

Yogyakarta: UGM Press.

Istimawan, & Dipohusodo. (1995). Menajemen PRoyek

dan Konstruksi Jilid I . Yogyakarta: Badan

Penerbit Kanisius.

Johannes, V., Sahureka, T. J. M., & Intan, S. (2023).

Pengaruh Penambahan Sikament-Nn Dan

Silica Fume Terhadap Kuat Tekan Beton SCC

(Self Compacting Concrete). Manumata, 9(I),

–163

Lukas Mose, V. Johannes, & Sahureka, Th. J. M. (2022).

Perbandingan kuat tekan beton degan

menggunakan agregat sungai desa tepa dan

pantai wati desa yatoke di pulau babar. Jurnal

Manumata, 8(1), 1–10.

Mahardho, F. T., Indriyani, R., & Wailuhu, Y. E. (2021).

Analisis Kinerja Waktu pada Proyek

Pembangunan Gedung Kampus II UIN Sunan

Ampel Surabaya. Jurnal Teknik ITS, 164-169.

Rahman, A. (2010). Manajemen Nilai Hasil pada Proyek

Konstruksi. Yogyakarta: Penerbit Andi.

Sobari, S., & Lutfi, M. (2018). Tinjauan Biyaya dan

Waktu Proyek South City Square LOT 2

Menggunakan Metode Earned Value. Jurnal

Universitas Muhamadiyah Jakarta , 1-7.

Soeharto, & imam. (1998). Manajemen Proyek: Dari

Konseptual Sampai Operasional. Edisi Kedua.

Jakarta: Erlangga.

Susanti, A., Setiawan, R., & Pratama, T. (2019). Analisis

Kinerja Jadwal dengan Metode Earned Value

Management. Jurnal Manajemen Proyek

Indonesia, 45-55.

Teknik Pantai. (1999). Dalam B. Triadmojo, Teknik

Pantai (hal. 119).

Triatmodjo, B. (1999). Teknik Pantai Abrasi di

Kabupaten Bengkalis. Yogyakarta: Betta Offset

.

Widiasanti, N., & Lenggogeni, A. (2013). Analisis

Kinerja Proyek Konstruksi dengan Metode

Earned Value. Jakarta: Universitas Indonesia

Diterbitkan

2025-01-28