Carrying capacity, Bore pile, Lateral loadAbstrak
To connect the separate road due to the stretching river, a bridge was built as a link. An important part of the bridge is the foundation. Wai Hina Bridge is located between the village of Haya and the village of Tehoru, district of Tehoru - Section of Jalan Haya-Tehoru. In the study, the carrying capacity of the soil will be calculated and re-planning the foundation using a bore pile foundation and calculating the lateral load of the soil against the abutment and pile and comparing the use of the efficiency of the number of piles between the pile and the bore pile. Calculation of the carrying capacity of the land using the Terzaghi method. Calculation of pole end resistance using the O'neil and Reese methods. Calculation of mast efficiency using the Converse-Labarre method. Calculation of the decrease in single piles and pile groups using the Empirical Vesic method. To calculate the lateral bearing capacity of the pole using the Broms method. At Wai Hina Bridge the foundation used is the bore pile foundation with a length of 20 m. In the abutment, a diameter of 0,50 m is used, with 19 poles. The carrying capacity of the pile group (Qg) is 46,044.59 kN and it is safe from the overloaded structure (P) of 15,500.61 kN. The horizontal force acting on the masthead (Hs) is 61,93 kN. The result of shear moment calculation is 8,30 > 1,5 and bolster moment 10,17 > 1,5. The pier diameter is used at the pier which is 0,70 m with 15 poles. The carrying capacity of the land (qu) is 18,077 kN / m². The carrying capacity of the pile group (Qg) is 55,953.19 kN and it is safe from the overloading structure (P) of 21,385.70 kN. The horizontal force acting on the masthead (Hs) is 100,62 kN. In terms of the amount of use of the bore, the pile is more efficient than the pile.Referensi
Anonim . 1992. Bridge Management System (BMS). Peraturan Perencanaan Teknik Jembatan. Departemen Pekerjaan Umum, Direktorat Jendral Bina Marga, Direktorat Bina Program Jalan.
Aspal, P., & Beton, P. (n.d.). Perhitungan perencanaan pembebanan jembatan.
Aspal, P., Beton, P., Priadi, E., Sc, M., Prayogo, K., Saptowati, H., … Setiyarto, Y. D. (2013). Analisis Beban Jembatan Data Jembatan. Journal of Chemical Information and Modeling, 53(9), 1689–1699. https://doi.org/10.1017/CBO9781107415324.004.
Departemen pekerjaan umum. (2007). Ahli Perencanaan Teknis Jembatan ( Bridge Design Engineer ).
Faizal, Zulkifli.2014. Analisis Struktur Pondasi Dan Abutment Jembatan Pada Proyek Jalan Tol Cimanggis-Cibitung.Skripsi.Bogor.
Fallis, A. . (2013). Journal. Journal of Chemical Information and Modeling, 53(9), 1689–1699. https://doi.org/10.1017/CBO9781107415324.004.
Fitri, Amanda Aisya.2017. Perencanaan Ulang Struktur Bawah Abutment Dengan Pondasi Bored Pile. Tugas Akhir. Jawa Tengah.
Jasso,Zonello. 2017. Tinjauan Perencanaan Pondasi Jembatan Wai Aleo II Dengan Menggunakan Bore Piel. Skripsi. Ambon.
Hardiyatmo H.C,2010. Mekanika Tanah I (Edisi Ke 5). Yokyakarta: Gajah MadaUniversity Press.
Hardiyatmo H.C,2014. Analisa Dan Perencanaan Fondasi I (Edisi Ke 3). Yokyakarta: Gajah Mada University Press.
Hardiyatmo H.C,2015. Analisa Dan Perencanaan Fondasi II (Edisi Ke 3). Yokyakarta: Gajah Mada University Press.
Maudin,Alpin.2017. Analisa Stabilitas Pondasi Bored Pile Pada Fly Over Simpang Surabaya Banda Aceh. Proposal Tugas Akhir. Banda Aceh Nasional, S. (2005). Standar pembebanan untuk jembatan.
Off, M., Sea, P., & Province, K. R. (2015). Karakteristik fisik dan mekanik tanah mengandung mineral timah di daerah laut payakundur, provinsi kepulauan riau. 45–53.
Prayogo, K., & Saptowati, H. (2016). Penyelidikan struktuur dan karakteriistik tanah untuk desain Pondasi Iridiatir Gamma kapasitas 2 MCi. Jurnal Perangkat Nuklir, 10(1978).
Riset, K., Pendidikan, T. D. A. N., Politeknik, T., Manado, N., & Teknik, J. (2016). PONDASI BORE PILE PROYEK PEMBANGUNAN.
Saputro, D. D. (2001). Studi pengaruh jarak tiang pancang pada kelompok tiang terhadap perubahan dimensi pile cap. 571, 85–93.
Standar Pembebanan Jembatan, Rsni T-02-2005 Struyk, H. J., dan Veen, K.H.C.W., 1984, Jembatan, PT. Pradnya Paramita, Jakarta
Unduhan
Diterbitkan
Terbitan
Bagian
Lisensi
Authors who publish with this journal agree to the following terms:- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).