Analisa Risiko Pada Proyek Rehabilitasi Gedung Arsip Unit Hidrologi Balai Sungai Wilayah Maluku
DOI:
https://doi.org/10.51135/manumatav8i2p167-176Kata Kunci:
Risk, Hydrological Building RehabilitationAbstrak
Project implementation in the construction services sector is faced with three obstacles, namely cost, time, and quality. These three constraints can be interpreted as project objectives, which are defined as cost-effective, timely, and quality-compliant. The successful implementation of a project carried out by a construction service company is related to the extent to which these three objectives can be met. In the construction work of the Archive Building Rehabilitation Project of the Hydrology Unit of the Maluku River Basin, this can be said to be a high-risk project. Considering the magnitude of the weight of the work which consists of the work of columns, beams and the height of the structure to be built. The construction process on this project usually takes a long time and is complex so that it can create uncertainty which will eventually lead to various kinds of risks. Based on the above background the author is interested in raising the title of the thesis "Risk Analysis in the Archives Building Rehabilitation Project of the Maluku River Basin Center with the aim of analyzing what risk faktors in the most dominant construction, knowing risk assessment, describing how to handle risks. From the results of the study, it was found that the risk faktors that are very dominant or significantly that often occur in projects are force majeure risk faktors, material and equipment risks and labor risks. From the results of faktor analysis calculations, three komponens are formed into three new faktors as total value Extraction Sums of Squared Loadings is more than one (total Extraction Sums of Squared Loadings . Material and equipment risk 20%, Management Risk 18%, Implementation Risk 17%, Force Majeure Risk 12%, Construction Risk 12%, Contractual Risk 11%, Labor Risk 10%. In the assessment of the 7 risks consisting of 17 indicators, there are 7 indicators that are included in the category of large risk (High Risk) and 10 other indicators are included in the category of moderate risk (Medium Risk). Based on the known risks, the control strategies or handling of potential risks that can be carried out are: Reducing the opportunity for yes risk and Reduce the impact of risk
Referensi
Abraham, Hendrita. (2016). Analisa Faktor-Faktor yang Mempengaruhi Kinerja Waktu Pelaksanaan Proyek Konstruksi di Wilayah Surabaya. Jurnal Rekayasa Teknik Sipil, Vol. 03 No 3. P. 55-63.
Asmarantaka, N.S. (2014). Analisis Risiko yang Berpengaruh Terhadap Kinerja Proyek pada Pembangunan Hotel Batiqa Palembang. Jurnal Teknik Sipil dan Lingkungan, Vol. 2 No 3. P. 483-491.
Kuniawan, B.Y. (2011). Analisa Risiko Konstruksi Pada Proyek Pembangunan Apartemen Petra Square Surabaya. Makalah Tugas Akhir Jurusan Teknik Sipil, Institut Teknologi Sepuluh November ( ITS ) Surabaya.
Labombang, Mastura. (2011). Manajemen Risiko dalam Proyek Konstruksi. Jurnal Smartek, Vol. 9 No 1. P. 39-46.
Nurlela & Heri Suprapto. (2014). Identifikasi dan Analisis Manajemen Risiko pada Proyek Pembangunan Infrastruktur Bangunan Gedung Bertingkat. Jurnal Desain Konstruksi, Vol. 13 No 2. P. 114-124.
Nasrul. (2015). Manajemen Risiko dalam Proyek Konstruksi Ditinjau dari Sisi Manajemen Waktu. Jurnal Momentum. Vol. 17 No 1. P. 50-54.
Yuliana, Chandra. (2017). Manajemen Risiko Kontrak untuk Proyek Konstruksi. Jurnal Rekayasa Sipil, Vol. 11 No 1.
Kadek Aditya Dei1 , G.A.P. Candra Dharmayanti2 , N. Martha Jaya2. Analisis Risiko Dalam Aliran Supply Chain Pada Proyek Konstruksi Gedung Di Bali. Jurnal Spektran, Vol. 5, No.1, Januari 2017, hal. 1-87.
Meylani, Rizka. (2018). Analisa Risiko Konstruksi pada Proyek Pembangunan Gedung. Tugas Akhir Jurusan Teknik Sipil, Universitas Sumatera Utara.
Monika Natalia, Riswandi, Zulfira Mirani, Yan Partawijaya, Merley Misriani. (2018). Faktor Penyebab Kegagalan Akibat Keterlambatan Proyek Konstruksi Pada Bangunan Gedung di Kota Padang. JIRS, Vol. XV No. 2
Unduhan
Diterbitkan
Terbitan
Bagian
Lisensi
Authors who publish with this journal agree to the following terms:- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).